Future of Energy Transmission in Maine

How Power Lines Work, Why New Ones Are Planned, And How You Can Have A Say

Featuring

Sharon Reishus, Reishus Consulting

Featuring

Rick Conant, RLC Engineering

Why We Made This Video

Plain Answers Before Big Decisions

New transmission is being planned for Maine, and the people who live and work near these projects have good questions: how the grid moves power, why new lines are needed, how projects are chosen and paid for, and what they mean for Maine. RENEW made this video to answer those questions in plain language, with Sharon Reishus of Reishus Consulting and Rick Conant of RLC Engineering walking through the basics. We want residents and communities to understand what’s being proposed and to know where and when they can weigh in.
Short Answers

Start Here: The Short Answers

Quick answers to the questions we hear most, pulled from the full conversation.

Short Answer – 01:27 – 03:33

What Is Transmission?

Short Answer – 03:40 – 04:34

Who Pays For Transmission

Short Answer – 05:36 – 06:30

Transmission As A Highway

Short Answer – 08:27 – 09:50

What Are The Benefits For Maine?

Short Answer – 11:52 – 13:10

How Long Do Transmission Projects Take?

Short Answer – 13:10 – 15:30

How To Explain Transmission To The Public

Short Answer – 26:08 – 28:11

How Can Communities Get Involved In Transmission Conversations

Short Answer – 28:37 – 29:15

Where Do Transmission Lines Go?

Short Answer – 35:22 – 39:56

Why We Can’t Always Build Underground

Watch

The Full Video

Jump to any chapter, or watch it start to finish.

Chapters
Loading chapters...
A plain-language conversation about how the electric grid moves power, why new transmission is being planned for northern Maine, how projects are chosen and paid for, and how residents and communities can take part. Watch it to understand the basics and know where to weigh in.
What’s Happening

Maine’s Role in New England’s Grid

Northern Maine has some of the best wind in New England, but very few power lines to carry that energy to the homes and businesses that need it. The main lines that carry power out of Maine are also close to full at times, and grid planners expect them to become a major bottleneck as the region adds more homegrown power. Two efforts now under way strengthen the regional grid. One upgrades the main lines that carry power from central Maine to the rest of New England. The other builds a new line into northern Maine and buys power from a new wind project there. They meet at Pittsfield, Maine: the new northern line ends there, and the regional upgrade carries the power onward. For Maine, that means a stronger, more reliable grid, new wind power built in the state, and a way to get it to customers. The cost of the regional upgrade is shared across all six New England states, and the northern Maine line and wind project are expected to bring Maine an estimated $387–425 million in net savings.

Regional Grid Upgrade

Strengthening the Region’s Main Power Lines

ISO New England, the nonprofit that runs the region’s power grid, asked companies for plans to move more power out of Maine. In August 2026 it chose a proposal from Central Maine Power and Eversource. Most of the work rebuilds or adds lines along existing power-line corridors. All six New England states share the cost, based on how much electricity each uses at peak times.


Cost: $2.2 billion Benefits: about $2.10 for every $1 In service: end of 2032 What happens next (ISO Newswire) →

Northern Maine Procurement

Connecting Northern Maine’s Wind to the Grid

Under a 2021 state law, the Maine Public Utilities Commission sought bids for new wind power in northern Maine and a line to deliver it. On August 25, 2026, it chose Avangrid, Central Maine Power’s parent company, to build a line from Haynesville to Pittsfield, and an 800-megawatt wind project from Clearway Energy in southeastern Aroostook County. Contracts, federal approval, permitting and community engagement are still ahead.


Line capacity: 1,200 MW Maine’s share of line cost: under 11% Est net savings for Maine: $387-425 million Maine PUC procurement page →

SITING & PERMITTING

Maine Transmission Infrastructure Study

Maine’s Department of Energy Resources has been working with the public and stakeholders on how the state should site and permit new power lines and involve communities along the way, with recommendations to the Legislature. RENEW has filed comments.
RESOURCES

Read More

RENEW COMMENTS

Comments to the Maine PUC on procurement of transmission and renewable energy for northern Maine

→

RENEW COMMENTS

Comments on the Maine Transmission Infrastructure Study

→

STATEMENT

MREA and RENEW: broad support for wind development in northern Maine

→

WHITE PAPER

High Voltage, High Stakes: Building the Grid New England Needs

→

ISO NEW ENGLAND

2050 Transmission Study

→

ISO NEW ENGLAND

2050 Transmission Study

→

ISO New England

Preferred Regional Transmission Solution Moves to Next Steps

→

ISO New England

Public Webinar Slides: Longer-Term Transmission Planning

→

ISO New England

Public Webinar Slides: Longer-Term Transmission Planning

→

ISO New England

Northern Maine Renewable Energy Development Program Procurement

→

GET INVOLVED

Have a say in Maine’s transmission decisions

Learn how to submit comments, speak at public hearings, and take part in decisions about new power lines, and sign up to hear when new opportunities open.